Multi-Sectoral Development Plan of District Mewat
under Ministry of Minority Affairs, Govt. of India, New Delhi |
|
The Govt. of India has
declared Mewat District as 90th Minority Concentrated
district. The Ministry has conducted survey of district Mewat
through Sociology Department, Mahrashi Dayanand University, Rohtak.
As per the gaps in the development identified in the survey report,
the MDA has submitted a project proposal to the Ministry of Minority
Affairs, Govt. of India through State Govt. Haryana.
The Ministry of Minority
Affairs, GOI has allocated an outlay of Rs. 34.20 crores for
district Mewat. The high empowered committee has approved an amount
of Rs. 1200.00 lacs under Education Component, Rs. 1779.61 lacs
under Health component, Rs. 324.00 lacs for Residential Girls Mewat
Model School at Khanpur Ghati and Mewat Model Public School at
village Madhi for Rs. 740.00 lacs. The detail of approved budget
under education and health component is given as under:- |
|
Approved Budget under
Education Component (Rs. in lacs) |
|
|
S.N. |
Sub Sector/Scheme |
Physical Target |
Financial Target
|
|
1. |
Construction of 05 Girls Hostel in Mewat Model School Taoru, F.P.
Jhirka, Hathin, Nagina and Punhana of 100 capacity @ Rs. 115.32 lacs per school |
05 |
576.60 |
|
2. |
Construction of 60 Class Rooms, 10 class rooms in each six Mewat
Model Schools i.e. Taoru, F.P. Jhirka, Hathin, Nagina, Punhana
and Nuh @ Rs. 61.33 lacs per 10 class rooms. |
60 |
367.98 |
|
3. |
Construction of 36 Staff Quarters in each Mewat Model School@
Rs. 37.57 lacs per six quarter. |
36 |
225.42 |
|
4. |
Setting up of Computer, Science Labs and Library @ Rs. 5.00 lacs
per school. |
06 |
30.00 |
| |
Total |
06 |
1200.00 |
|
|
|
|
Approved Budget for 05
PHCs (Marora, Mohd. Pur Ahir, Biwan, Uttawar
and Singar) and 01 CHC at Pinangwan under Health Component (Rs.
in lacs) |
|
|
|
S.N. |
Sub Sector/Scheme |
Central Share |
State Share |
Total |
|
1. |
Construction of 05
PHCs @ Rs. 208.69 lacs per PHC |
886.93 (85%) |
156.52 (15%) |
1043.45 |
|
2. |
Construction of CHC
@ Rs. 531.16 lacs |
451.49 (85%) |
79.67 (15%) |
531.16 |
|
3. |
Equipment &
Furniture for PHCs |
127.50 (85%) |
22.50 (15%) |
150.00 |
|
4. |
Equipment &
Furniture Fixture for CHC |
46.75 (85%) |
8.25 (15%) |
55.00 |
| |
Total |
1512.67 |
266.94 |
1779.61 |
|
|
|
Approved Budget for
Residential Girls Mewat Model School at Khanpur Ghati (Rs. in lacs) |
|
|
S.N. |
Sub Sector/Scheme |
Physical Target |
Central Share |
State Share |
Total |
|
1. |
Construction of Residential Girls Mewat Model School at Khanpur
Ghati |
01 |
243.00 (75%) |
81.00 (25%) |
324.00 |
| |
Total |
|
243.00 |
81.00 |
324.00 |
|
|
|
Approved Budget for
Mewat Model Public School at Madhi (Rs. in lacs) |
|
|
S.N. |
Sub Sector/Scheme |
Physical Target |
Central Share |
State Share |
Total |
|
1. |
Construction of Mewat Model Public School at village Madhi
(School of Science and Math) |
01 |
454.33 |
285.67 |
740.00 |
| |
Total |
|
454.33 |
285.67 |
740.00 |
|
|
The construction work has been allotted to National Building
Construction Corporation, New Delhi (Govt. of India Undertaking).
The construction work is in progress. The construction work has been
allotted to XEN. PWD (B&R), Nuh for Residential Girls Model School
at Khanpur Ghati and Mewat Model Public School, Madhi. The
construction work is in progress. |
|
|
|
|
Name of Executing Agency |
National Building Construction
Corporation, New Delhi (Govt. of India Undertaking) and PWD
(B&R) Mewat |
|
|
Physical
Progress |
|
|
S.N. |
Sub Sector/Scheme |
Unit |
Status |
Expected Date of
Completion |
|
1. |
Construction of Girls Hostel |
05 |
Work in progress |
31-12-12 |
|
2. |
Construction of Class Room |
60 |
Completed |
Completed |
|
3. |
Construction of Staff Quarters |
36 |
Work in progress |
30-06-12 |
|
4. |
Construction of PHCs |
05 |
Work in progress |
30-06-12 |
|
5. |
Construction of CHC |
01 |
Work in progress |
31-12-12 |
|
6. |
Construction of Residential Girl Model School |
01 |
Tender
under process |
-- |
|
7. |
Construction of Mewat Model Public School |
01 |
Tender
under process |
-- |
|
Total |
|
|
|
|
|
(Click
below) |
|
Photo Gallery of
Construction Works under MsDP |
|
List of
Villages where assets are to be created |
Nuh, Taoru,
Nagina, Punhana, F.P. Jhirka, Hathin, Marora, Mohd. Pur Ahir, Biwan,
Uttawar, Singar, Pinangwan. |
|
Physical and
Financial Progress Report |